Wednesday, June 20, 2012

Glendale Blvd: Road Closure Update

Map: DWP.  River Supply Conduit Lower Reach 4 Improvement Project causing traffic and trouble breathing in the neighborhood north of Fletcher on Glendale Blvd.  (Click on image to enlarge.)

DWP sent out an email late Tuesday announcing temporary no right turn from Fletcher onto Glendale Blvd starting Wednesday. Copied directly from the email:

Temporary lane closure of right-turn lane on Fletcher Drive starting June 20: Construction activities will require a temporary closure of the right-turn lane from Fletcher Drive onto Glendale Boulevard, which will be in effect:

June 20-22: 8 am to 5 pm

June 25  at 7 a.m. through June 27 at 6 a.m.

If necessary, the right-turn lane closure may be extended to include:

June 27-29: 7 a.m. to 6 p.m.
June 30: 8 a.m. to 5 p.m.

More Info: www.ladwp.com/RSC4

Related Glendale Blvd traffic news: The Eastsider